Power shutdown areas in Tiruchirapalli - April 2021


Power Shut Down (01-04-2021 to 30-04-2021)

The power supply will be suspended in the following areas on (01-04-2021 to 30-04-2021) from 09:00 am to 05:00 pm for maintenance work. Supply will be resumed before 05:00 pm if the works are completed.


TANGEDCO Outages Details
Outage date Town Substation Feeder Area affected From To
27-04-2021 Trichy THATHIENGARPET 110/33-22-11 KV SS THATHIENGARPET 110/33-22-11 KV SS MELA KOTHAMPATTY ,SJLT SPINNING MILL ,URAKARAI ,DEVANUR PUTHUR ,MANIKAPURAM ,AARAICHY ,SAKKAMPATTY ,VALAIYATHUR, MAHADEVI ,PACHAPERUMAL PATTY ,ALATHUDAIYAN PATTY, PERUGANUR ,KALINGAPATTY 09:45 17:00
27-04-2021 Trichy AMMAPETTAI 110/11 KV AMMAPETTAI 110/11 KV THAYANURSANTHAI,KALLKUDY,ENNAMKULATHUR,ALAMPATTYPUTHUR,VELLIVADAI,AMMAPETTAI ,KARIYAMPATTY,MARAVANU SAMUTHIRAM,CHATHIRAPATTY,RAMJI NGR,SAMATHUVAPURAM 09:45 14:00
27-04-2021 Trichy SIRUGANUR 110/22 KV SS SIRUGANUR 110/22 KV SS THIRUPPUR,REDDIMANGUDY,MRPALAYAM,OODATHUR,NEDUNTHUR,NAMBAKURICHI,NEILULAM,MANIYAKURICHI,SADAMANGALAM 08:00 18:00
28-04-2021 Trichy ATHAVATHUR 110/11KV SS ATHAVATHUR 110/11KV SS PULIYUR,THAYANUR,PUNGANUR,INIYANUR,SOMARASAMPETTAI,KULUMANI,VAYALUR,NACHIKURICHI,MULLIKARUMBUR,ETTARAI,KOPPU,ALLDURAI,PERIYA KARUPPUR,MALLIYAMPATHU 09:45 16:00