Power Shut Down (01-05-2021 to 30-05-2021) The power supply will be suspended in the following areas on Today (01-05-2021 to 31-05-2021...
Power Shut Down (01-05-2021 to 30-05-2021)
The power supply will be suspended in the following areas on Today (01-05-2021 to 31-05-2021) from 09:00 am to 02:00 pm for maintenance work. Supply will be resumed before 02:00 pm if the works are completed.TANGEDCO Outages Details | |||||
---|---|---|---|---|---|
Outage date | Town | Substation | Area affected | From | To |
04-05-2021 | P.Velur | JEDARPALAYAM 110/11 KV | V.G Attur,Jedarpalayam,Naickanoor,K.M.Devi | 09:00 | 14:00 |
06-05-2021 | Rasipuram | NAMAGIRIPET 110 KV | Koraiyaru,Pudupatty,Namagiripet Town,Pachudaiyampalayam,CWSS,Pattanam | 09:00 | 14:00 |
07-05-2021 | Namakkal | NAMAKKAL 110/22 KV | Namakkal Water Works,Aniyapuram,Thoosur,Local - I,Local - II,Muthugapatty,Mudalaipatty,Keerambur,Collectorate,Local - III,Thottipatty | 09:00 | 14:00 |
12-05-2021 | Namakkal | S.VALAVANTHI 110 KV GRID | Keelsathamboor,Aniyapuram,Nanjai Idayar,Ariyur,Mohanur,Paramathy,Auto Nagar | 09:00 | 14:00 |
21-05-2021 | P.Velur | VILLIPALAYAM 110/22 KV SS | Gajendra nagar,Thimmakali,Pillaikalathur,Kudacherry,Keelakkadai | 09:00 | 14:00 |
25-05-2021 | Tiruchengode | TIRUCHENGODE 110 KV | Raja Goundampalayam,South Urban,North Urban,Mill,Gollapatty,Devanankurichy,Palamadai,Water Works,Varagoorampatty,Workshop | 09:00 | 14:00 |
25-05-2021 | Namakkal | PUDAN SANTHAI 110 KV | Karaikurichy,Puduchatram,Kolathupalayam,Elur,Sellappampatty,Mobagas,230 KV | 09:00 | 14:00 |
26-05-2021 | P.Velur | KABILARMALAI 110 KV | Velur,Pothanur,Veeranampalayam,Pandamangalam,Pillikkalpalayam,Jedarpalayam,Kothamangalam,Ayyampalayam,Industrial,TWAD,Dedicated(Kabilakurichi) | 09:00 | 14:00 |
29-05-2021 | P.Velur | P.VELUR 110 KV | Nalliyampalayam,Velur,Pothanur,V,Suriyampalayam,Devarayasamuram,Paramathy | 09:00 | 14:00 |